In Scrum, how does the Development Team select items from the Product Backlog?

Prepare for the Professional Scrum Master (PSM) III Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

In Scrum, the Development Team selects items from the Product Backlog in collaboration with the Product Owner. This collaboration is essential because the Product Owner represents the stakeholders and has the best understanding of the market needs and priorities. The Development Team gains insights into the value and urgency of the backlog items, allowing them to make informed decisions about what to work on next.

Effective collaboration ensures that the team understands the context and the requirements behind the items to be developed. This prioritization process allows the team to align their efforts with the broader goals of the organization and ensures that they are working on the most valuable items.

The dynamic between the Development Team and the Product Owner is vital for balancing considerations of technical feasibility with business value, resulting in better planning and outcomes for the sprint. This collaborative selection process is a key aspect of Scrum that fosters teamwork and communication, ultimately driving the effectiveness of the Scrum framework.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy