In Scrum, who is accountable for ensuring maximized value from the development effort?

Prepare for the Professional Scrum Master (PSM) III Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

In Scrum, the Product Owner holds the accountability for maximizing the value derived from the development effort. This role is primarily responsible for managing the product backlog, which includes prioritizing items based on stakeholder feedback, market demands, and the overall vision for the product. The Product Owner must balance various factors, such as customer needs and technical feasibility, to ensure that the most valuable features are delivered in a timely manner.

The Product Owner's decisions directly influence what the Development Team works on and the order in which they tackle backlog items. This strategic prioritization is essential not only for delivering high-impact features but also for aligning the work with organizational goals and customer satisfaction.

While the Development Team plays a critical role in delivering the product increment and is focused on the technical implementation, they do not make decisions about prioritization or value maximization. The Scrum Master's role is to facilitate Scrum processes and help remove impediments for the team but does not include accountability for the value delivered. Stakeholders provide feedback and contribute to the product vision, but they do not have the direct responsibility for maximizing value in the same way the Product Owner does, as they are not involved in the day-to-day management of the product backlog.

In summary, the Product Owner is uniquely positioned to ensure that