What does the term 'release burndown' refer to in Scrum?

Prepare for the Professional Scrum Master (PSM) III Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

The term 'release burndown' specifically refers to a measure of the remaining Product Backlog throughout a release plan. It is a visual representation that shows the amount of work left to complete in order to deliver a product increment, typically plotted against time across the release cycle. This chart helps Scrum teams track their progress toward the completion of features or capabilities expected in a particular release, providing insights into how much work remains and whether the team is on track to meet release deadlines.

By monitoring the release burndown, teams can better forecast their progress, identify potential risks to delivery, and make necessary adjustments to their work strategy. Understanding the remaining work is crucial for ensuring that stakeholders are aware of the status of the project and that the team remains focused on delivering value within the planned time frame.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy