What is the key focus of a Sprint Planning meeting?

Prepare for the Professional Scrum Master (PSM) III Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

The key focus of a Sprint Planning meeting is to plan the work to be performed in the Sprint. This meeting serves as the cornerstone for organizing the team's efforts during the Sprint. By effectively collaborating, the Scrum Team breaks down the work into manageable tasks, ensuring that everyone understands the goals and priorities for the upcoming Sprint.

During this meeting, the team discusses the items from the Product Backlog, selects which items they can commit to completing, and develops a plan for how to accomplish this work. This collaborative planning not only fosters clarity but also aligns the team’s efforts toward delivering the highest value possible, enhancing the overall effectiveness of the team's output.

The other activities listed do not align with the primary purpose of Sprint Planning. Reviewing team performance typically occurs during retrospectives, finalizing product design is usually part of a different phase of development, and training new team members is not a direct focus of Sprint Planning. The emphasis during Sprint Planning is purely on what work will be taken into the Sprint and how it will be executed, making the selected answer the most accurate representation of the meeting's purpose.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy