What is the maximum duration of a Sprint according to Scrum guidelines?

Prepare for the Professional Scrum Master (PSM) III Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

The Scrum framework specifies that the maximum duration of a Sprint is one month. This guideline is in place to ensure that teams can regularly deliver potentially releasable product increments, allowing for frequent feedback and adaptation. Keeping the Sprint to a maximum of one month promotes sustainability and helps maintain a regular cadence for the Scrum Team.

Shorter Sprints can provide additional opportunities for reviews and adjustments, but even the longest Sprints should not exceed one month. This ensures that the Scrum Team remains focused on delivering value in a manageable timeframe, allowing them to inspect and adapt their work frequently which aligns with the Agile principles of flexibility and responsiveness to change.

By adhering to this guideline, organizations can foster a culture of continuous improvement, allowing teams to evaluate their progress more effectively, make necessary adjustments, and enhance collaboration.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy