What is the maximum length a Sprint can be?

Prepare for the Professional Scrum Master (PSM) III Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

The maximum length of a Sprint is one month. This guideline is established in the Scrum framework to ensure that the time-boxed nature of Sprints facilitates regular delivery of potentially releasable increments of the product. A month-long Sprint allows the team to plan and execute their work effectively while receiving feedback in a timely manner.

Limiting the duration to a month also supports agility, enabling teams to adapt quickly to changes in requirements or market conditions. If Sprints were to extend beyond that timeframe, the risks and uncertainties would increase, making it harder to manage expectations and deliver tangible results. The emphasis on shorter Sprints, such as one to four weeks, encourages teams to maintain focus and momentum while continuously inspecting and adapting their work process.

Choosing any length beyond one month, such as two, three, or six weeks, would violate the maximum duration defined by Scrum guidelines, which is intended to create a consistent rhythm for development that balances productivity with responsiveness. Thus, adhering to the one-month maximum reinforces the principles of iterative progress and continuous improvement central to Scrum.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy