When is the only time stakeholders and the Scrum Team can come together?

Prepare for the Professional Scrum Master (PSM) III Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

The only time stakeholders and the Scrum Team come together specifically for formal interaction is during the Sprint Review. This event is designed to showcase the work completed during the Sprint and gather feedback from stakeholders. The intent is to assess what has been accomplished, discuss what remains, and adjust the Product Backlog if necessary based on stakeholder input. The Sprint Review fosters collaboration and communication between the Scrum Team and stakeholders, making it an essential opportunity for alignment and feedback.

While other events like Sprint Planning involve the Scrum Team and stakeholders may occasionally participate, the Sprint Review is the structured occasion dedicated to stakeholder interaction with the Scrum Team, ensuring alignment with their needs and expectations. This focus on stakeholder collaboration is fundamental to ensuring that the product delivered is relevant and valuable.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy