When is the Sprint Backlog created?

Prepare for the Professional Scrum Master (PSM) III Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

The Sprint Backlog is created during the Sprint Planning meeting. This is a key event in the Scrum framework where the Scrum Team collaborates to define the work that will be undertaken during the upcoming Sprint. It involves selecting items from the Product Backlog that the team believes can be completed in the Sprint and defining the work necessary to deliver those items.

The Sprint Backlog serves as a dynamic plan for the team's work during the Sprint, allowing for adjustments as necessary and reflecting the team's commitments to the Sprint Goals. By forming the Sprint Backlog in the Sprint Planning meeting, the team sets clear objectives and a shared understanding of the tasks for that Sprint, which is crucial for maintaining focus and alignment.

Creating the Sprint Backlog at this stage enables the team to start the Sprint with a clear vision of their tasks, helping ensure that alignment and transparency are maintained throughout the execution of the Sprint.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy