Which role is responsible for prioritizing the work on the Sprint Backlog?

Prepare for the Professional Scrum Master (PSM) III Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

The role responsible for prioritizing the work on the Sprint Backlog is the Product Owner. This is aligned with the fundamental principles of Scrum, where the Product Owner serves as the primary stakeholder representative and is tasked with maximizing the value of the product resulting from the work of the Development Team.

In managing the Sprint Backlog, the Product Owner ensures that the most valuable features are prioritized based on factors such as stakeholder input, market demands, and alignment with the overall product vision. This also includes continuous collaboration with the Development Team to refine and adjust priorities as necessary throughout the Sprint.

This responsibility is crucial because it directly influences how the Development Team allocates its time and effort during the Sprint, ultimately impacting the product's success and the stakeholders' satisfaction.

The other roles listed have different focuses; for instance, the Scrum Master facilitates the Scrum process and ensures that the team adheres to Scrum principles, while the Development Team is responsible for delivering the work but does not prioritize it. Stakeholders inform and provide input, but they are not responsible for setting priorities on the Sprint Backlog, as that responsibility lies with the Product Owner.