Which Scrum event focuses on identifying improvements for future Sprints?

Prepare for the Professional Scrum Master (PSM) III Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

The Scrum event that specifically focuses on identifying improvements for future Sprints is the Sprint Retrospective. This event occurs at the end of each Sprint and serves as a key opportunity for the Scrum Team to reflect on the past Sprint. During the Sprint Retrospective, team members discuss what went well, what didn't, and how they can enhance their processes and practices moving forward.

The aim is to create a safe environment where team members can openly share their thoughts, leading to actionable insights that can improve both the team's dynamics and their overall productivity. By focusing on continuous improvement, the Sprint Retrospective supports the Scrum principles of adaptation and transparency, ensuring that the team can evolve and become more effective in their work.

In contrast, other Scrum events have different purposes: Sprint Planning is centered around defining what will be accomplished in the upcoming Sprint; the Sprint Review involves stakeholders and focuses on inspecting the product increment and adapting the backlog; while the Daily Scrum is a brief check-in meeting aimed at synchronizing activities and addressing any impediments. Thus, while each of these events plays a crucial role in the Scrum framework, the Sprint Retrospective uniquely prioritizes identifying improvements for the future.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy