Which team is responsible for ensuring that the Product Backlog items meet the Definition of "Done"?

Prepare for the Professional Scrum Master (PSM) III Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

The Development Team holds the responsibility for ensuring that the Product Backlog items meet the Definition of "Done." This accountability is central to the Scrum framework, as the Development Team is composed of professionals who are responsible for delivering a potentially releasable increment of the product at the end of each Sprint.

The Definition of "Done" is a shared understanding among the team of what it means for work to be complete. It includes criteria such as coding, testing, documentation, and any other requirements that must be satisfied for the work to be considered finished. The Development Team assesses each Product Backlog item against this Definition to ensure high-quality delivery and maintain consistency.

This responsibility is pivotal because it empowers the Development Team to own their work and fosters a culture of quality. By having the Development Team accountable for meeting the Definition of "Done," it allows for transparency and reinforces the self-managing nature of the Scrum framework.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy