Who is responsible for tracking the remaining work of the Sprint?

Prepare for the Professional Scrum Master (PSM) III Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

The Development Team is responsible for tracking the remaining work of the Sprint because they are the ones engaged in creating the Increment and completing the work defined in the Sprint Backlog. In Scrum, the Development Team has the autonomy to self-manage their workflow and progress. This includes monitoring how much work has been completed and how much remains, allowing them to assess their capacity for the Sprint and make any necessary adjustments to ensure they meet the Sprint Goal.

By tracking remaining work, the Development Team can maintain transparency about their progress, which is essential for effective collaboration both within the team and with stakeholders. They utilize tools such as burn-down charts or task boards to visualize this progress. The Scrum Master facilitates this process but does not track the remaining work, as it's primarily a responsibility of the Development Team. The Product Owner focuses on the product backlog items and ensuring the right items are prioritized, while project stakeholders rely on the information provided by the team but are not directly involved in the tracking of work during the Sprint.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy