How is ownership of a Sprint Backlog Item viewed within the Development Team?

Prepare for the Professional Scrum Master (PSM) III Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

The correct perspective is that all items in the Sprint Backlog are owned collectively by the entire Development Team. In Scrum, the Sprint Backlog is a commitment by the Development Team to deliver a specific set of outcomes during the Sprint. This collective ownership fosters collaboration, accountability, and shared responsibility among team members.

When the Development Team operates as a unit, it encourages members to support each other, share knowledge, and work together towards a common goal. This approach not only enhances commitment to the Sprint goals but also allows team members to step in and assist each other as needed, which can lead to faster problem resolution and more effective progress toward delivering the increment.

The idea of individual ownership, where each item is owned by solely the individual working on it, contrasts with this collaborative spirit by potentially leading to siloed thinking and a lack of team cohesion. Additionally, the notion that only the Scrum Master or no one owns the items does not align with the core principles of Scrum, which emphasize collaboration and collective responsibility within the Development Team.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy