Is a Scrum Team allowed to meet with stakeholders outside of Sprint Review?

Prepare for the Professional Scrum Master (PSM) III Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

The assertion that a Scrum Team is not allowed to meet with stakeholders outside of the Sprint Review is misleading. In fact, Scrum encourages open communication and collaboration between the Scrum Team and stakeholders at any time.

The primary context of the Sprint Review is to inspect the Increment and adapt the Product Backlog based on stakeholder feedback. However, this does not prohibit additional interactions at other times. Teams can (and often do) meet with stakeholders to clarify requirements, gather feedback, or discuss project status outside the formal events defined in Scrum.

The real focus should be on the principle of collaboration and ensuring that all stakeholders have the opportunities to provide input throughout the development process, not limited to specific Scrum events. This flexibility is essential for adapting to changing requirements and fostering a collaborative environment.

So, while the assertion that Scrum Team meetings with stakeholders outside of the Sprint Review is forbidden is incorrect, understanding the flexibility and encouragement for such engagements is crucial for effective product development within the Scrum framework.