What activity typically takes place during the Daily Scrum?

Prepare for the Professional Scrum Master (PSM) III Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

During the Daily Scrum, team members focus on discussing their progress and any impediments they may be facing. This meeting is essential for enhancing collaboration and ensuring that the team stays aligned with its goals. Each member typically answers three questions regarding what they accomplished since the last meeting, what they plan to achieve before the next one, and any obstacles they might be encountering.

This process allows team members to openly communicate, share insights, and collectively address challenges, fostering a sense of accountability and teamwork. The Daily Scrum is designed as a quick and focused touchpoint that supports the Scrum framework's principles of transparency and inspection, helping the team adapt to changing situations effectively without external influences.

In contrast, logging hours, receiving external feedback, or assigning new tasks do not align with the core purpose of the Daily Scrum. The moment is primarily owned by the team and aims to facilitate their self-management and iterative progress in the sprint.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy