What does the Sprint Burndown chart illustrate during the Sprint?

Prepare for the Professional Scrum Master (PSM) III Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

The Sprint Burndown chart primarily illustrates the estimated work remaining in the Sprint over time. This visual tool helps the Scrum Team and stakeholders track progress towards completing the Sprint Goal by showing how much work has been completed versus how much is left.

As the team works through their tasks and completes them, the amount of remaining work decreases, ideally approaching zero by the end of the Sprint. This real-time visualization allows the team to assess whether they are on track to complete the planned work within the Sprint duration. It fosters transparency and facilitates discussions around progress, potential roadblocks, and necessary adjustments to the team's work habits.

Understanding the burndown chart is crucial for Scrum Masters, as it informs decision-making and helps the team remain aligned and accountable throughout the Sprint.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy