Which of the following roles is NOT part of a Scrum Team?

Prepare for the Professional Scrum Master (PSM) III Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

The role that is not part of a Scrum Team is the Project Manager. In Scrum, the framework is designed around specific roles that facilitate collaboration and self-organization within the team. The Development Team, Product Owner, and Scrum Master are the three core roles defined in Scrum.

The Development Team consists of professionals who work together to deliver potentially releasable increments of a product at the end of each Sprint. The Product Owner is responsible for maximizing the value of the product and managing the product backlog. The Scrum Master serves as a facilitator for the Scrum Team, helping to ensure that Scrum practices are followed, and fostering an environment for effective collaboration.

Project Manager, as a traditional role, generally entails a more directive and controlling approach to managing projects, which is not aligned with the self-managing principles of Scrum. Instead of a Project Manager, the Scrum roles distribute responsibilities among the Product Owner, Scrum Master, and Development Team, ensuring everyone collaborates towards achieving the project objectives while enabling flexibility and responsiveness to change.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy