Who is required to attend the Daily Scrum?

Prepare for the Professional Scrum Master (PSM) III Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

The correct answer emphasizes that the Daily Scrum is an event specifically designed for the Development Team. This time-boxed meeting, typically lasting 15 minutes, focuses on the progress of the work and is an opportunity for team members to coordinate their efforts and maximize the efficiency of their collaboration.

During the Daily Scrum, developers discuss their achievements since the last meeting, outline their plans for the next day, and highlight any impediments they are facing. This focus on the Development Team ensures that members are aligned and can effectively manage their work towards the Sprint Goal.

While the Scrum Master may attend the Daily Scrum, their presence is not mandatory as the meeting is primarily for the Development Team to self-manage and synchronize daily activities. The Product Owner does not have a required role in this event, although they may choose to attend to gain insights into team progress. The emphasis on the Development Team's presence underlines the Agile principle of empowering the team to determine how to best accomplish their work. Therefore, the Daily Scrum is fundamentally a Development Team meeting.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy