Who is responsible for clearly expressing Product Backlog Items?

Prepare for the Professional Scrum Master (PSM) III Test. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

The correct answer is the Product Owner, as they hold the responsibility for clearly expressing Product Backlog Items. In Scrum, the Product Owner acts as the intermediary between the stakeholders and the Development Team, ensuring that the product being developed aligns with customer needs and business goals.

The Product Owner must maintain a well-structured and prioritized Product Backlog that effectively communicates the vision, objectives, and requirements for the product. This includes writing clear and concise Product Backlog Items (PBIs) that provide the necessary information and context for the Development Team to understand what is needed. When PBIs are well-defined, it helps the Development Team to accurately estimate effort and plan their work, ultimately leading to a more efficient development process and better product outcomes.

In summary, the Product Owner’s role in clearly expressing Product Backlog Items is crucial for ensuring everyone involved in the Scrum process has a shared understanding of the product goals and priorities.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy